Description
Local report on activities done within the TRD-2D project for CBM
TRD-2D Addendum follow up (27.11.2021)
- Reconstruction software to be ported to CbmRoot
- Test CA track finder with the new software
- Build the pT spectra for the new CA tracking/additional to STS.
Regular weekly informal meetings between AB, VF and SG on Friday.
To discuss the progress at beginning of November with TC and the TRD/Soft team and take some decision.
TRD-2D @ mCBM (15.11.2021 ?!)
- FASP reconstruction
- Analyze the PRF distribution on local settings (Claudiu 30.11.21)
- Test the new optical connection on the CROB @ GSI (Claudiu 12.10.21)
- SPADIC reconstruction
- Tracking (Alex)
- ToF CR runs
- After CROB positive test we should join ToF runs (Claudiu, Alex 30.10.2021)
TRD-2D EDR (?!)
- Construction of a full sized TRD-2D prototype. Entrance window with AL+C fibre (Joerg, Laura, 15.10.2021)
- Tutorial for the winding machine and wire tension measurements (Cristi, Laura, George, Andrei, 30.10.2021)
- Generate construction manual V0 with skeleton steps
- Finalize module and construction manual estimated deadline (15.02.2022)
- Local Tests of entrance window absorbtion (Fe, X-rays) (15.03.2022)
- CERN-PS tests for PID (06.2022 ???). What DAQ can be used @ CERN?