    • 09:00 09:05
      Intro 5m
      Speakers: Alexandru Bercuci (IFIN-HH), Andrei Herghelegiu (National Institute of Physics and Nuclear Engineering (IFIN-HH)), Claudiu Schiaua (IFIN-HH/DFH), Gheorghe Caragheorgheopol (National Institute of Physics and Nuclear Engineering (IFIN-HH)), Laura Radulescu (IFIN-HH), Mariana Petris (National Institute for R&D in Physics and Nuclear Engineering (IFIN-HH), Bucharest), Prof. Mihai Petrovici (National Institute for Physics and Nuclear Engineering (IFIN-HH)), Vasile Catanescu (National Institute of Physics and Nuclear Engineering (IFIN-HH))
    • 09:05 09:25
      mCBM June campaign 20m

      U beam, June 18-21, 2024:

      • We will start presumably at 08:00 CET to setup the U beam into our cave, until 10:00 CET latest we should have U beam, 1.06AGeV in our cave.
      • Most likely On Fri., June 21, 2024, 08:00 CET our U campaign will end.
      Speaker: Alexandru Bercuci (IFIN-HH)
    • 09:25 09:55
      Prototype production status 30m
      Speakers: Laura Radulescu (IFIN-HH), Mr Andrei Radu (IFIN-HH), Mr Andrei Naziru (ELI-NP), Andrei Herghelegiu (National Institute of Physics and Nuclear Engineering (IFIN-HH))
      • constructia  prototipurilor
        • finalizare HC pt backplane (Florin / George / Vali) [1.04 -
        • degajari pt flat-uri la ProPlastic (Laura), Se foloseste BP testat cu laser pentru productie
        • cutiutele de gaz - de finisat [27.03 -
      • Asamblare
        • ferestrele de intrare (R Andrei) [9.04 -
      • Fire Anodice 
        • aliniere anod vs catod (Andrei N/Alex) https://indico.nipne.ro/event/287/  - 22.03 [done]
          • CNC QA (Garbel)
          • finalizat componente de protectie si rama de fixare detector [15.05]
        • test final RAMA + ALINIAMENT [29.03 -
      • FEE
        • FW - implementare relativ intarziata de bug-uri in sistemul de sintetizare.
      • HV box : 
        • PCB (Cara/Bugi/Claudiu) achizitie de piese [running]
        • PCB design [done]
          • de identificat o lista de componente comercial disponibile.
        • Surse ISEG : CBM OK, pret ???, incercam o integrare LV + HV + pulser (Claudiu, Alex, Laura, Cara)
    • 09:55 10:15
      FASP bonding [on hold] 20m
      • final conclusions
      • strategy
        TBD* after mCBM24 data taking campaign
      Speaker: Claudiu Schiaua (IFIN-HH/DFH)

      de discutat dupa campania de la mCBM