Please upload your talks before meeting starts

TRD-2D weekly

Europe/Bucharest
Conference room Building A (DFH)

Conference room Building A

DFH

Alexandru Bercuci (IFIN-HH)
Description

  Weekly reports on local activities done for the TRD-2D project of the CBM collaboration.

Meeting Access Information

    • 1
      Intro
      Speakers: Alexandru Bercuci (IFIN-HH), Andrei Herghelegiu (National Institute of Physics and Nuclear Engineering (IFIN-HH)), Claudiu Schiaua (IFIN-HH/DFH), Gheorghe Caragheorgheopol (National Institute of Physics and Nuclear Engineering (IFIN-HH)), Laura Radulescu (IFIN-HH), Mariana Petris (National Institute for R&D in Physics and Nuclear Engineering (IFIN-HH), Bucharest), Prof. Mihai Petrovici (National Institute for Physics and Nuclear Engineering (IFIN-HH)), Vasile Catanescu (National Institute of Physics and Nuclear Engineering (IFIN-HH))

      From the official summary of the Council by the FAIR Management:

       

      • “Good news on additional shareholder contributions: Poland (formal letter from Poland will follow until end July 2024), France, Sweden
      • Good news regarding the commissioning budget: the proposed commissioning budgets were supported by the CSG and commissioning budgets have been released by the Council for the years 2024 and 2025 as a new budgetline with additional budget.
      • Good solution process regarding power cables from India: critical Inkind supply by India urgently needed in line with the site installation process.
      • Good news regarding time critical components for CBM beamline - magnets and vacuum components: the Council is supporting the procurement of these time critical items as long as the overall budget situation is positive. With the formal confirmation of the contribution from Poland end of July 2024 a decision in writing will be initiated to approve this procurement step. The tendering process for these components can start already immediately.
      • The next Council meeting in December 2024 will take place in Kolkata, India with the hope that in the phase towards this meeting in December 2024 the Indian shareholder can make steps forward in granting an additional contribution for FAIR.”

      This means we have a beamline to the CBM cave approved!

       

      Tetyana Galatyuk

               on behalf of the CBM Management Board


       


       

    • 2
      Prototype production status
      Speakers: Laura Radulescu (IFIN-HH), Mr Andrei Radu (IFIN-HH), Mr Andrei Naziru (ELI-NP), Andrei Herghelegiu (National Institute of Physics and Nuclear Engineering (IFIN-HH))
      • constructia  prototipurilor
        • montarea back-plane (R. Andrei, V Aprodu, G. Stoian) [1.07 - 
          • se achizitioneaza inca 4 x 2 elemente pentru back-plane (pad-plane + ecran + flat-uri).
            • se fac modificarile tehnologice la pad-plane (Bugi) 
          • Se foloseste honeycomb deteriorat termic. SE cere oferta pt 8 pcs.
          • se cere oferta pt 8 seturi complete baghete
          • Clinceni - oferta pentru C+Kapton (8 pcs)
          • achizitie Kapton 
        • winding + asamblare (A. Naziru, M. State, A. Herghelegiu, C. Andrei, etc) [15.07 - 
          • Madalina - contributie la Manual si QA
        • ansamblu fereastra de intrare
          • modificari la proiectul datorate experientei de constructie (Laura, R Andrei)
        • testare (team) [25.08 - 

      ==============================================================================

      • Asamblare
        • 2 x ferestrele de intrare (R Andrei) [9.04 - 21.05]
        • pad-plane [1.07 -
      • Fire Anodice 
        • aliniere anod vs catod (Andrei N/Alex) https://indico.nipne.ro/event/287/  - 22.03 [done]
          • NUC - functional !!!
          • conexiuni - finalizate, trese - de asamblat (26.06 - )
        • test final RAMA + ALINIAMENT [29.03 -
      • HV box : 
        • PCB (Cara/Bugi/Claudiu) achizitie de piese [running]
        • PCB design [done]
          • de identificat o lista de componente comercial disponibile.
        • Surse ISEG : CBM OK, pret ???, incercam o integrare LV + HV + pulser (Claudiu, Alex, Laura, Cara)
    • 3
      Acquisitions and puchase
      • backplane components
      Speaker: Laura Radulescu (IFIN-HH)
      • Numar de camere care se doresc a fi construite ?
        • 10 camere ! 
      • Honeycomb 20mm 
        • oferta de pret 10 buc [19.08 -
      • Honeycomb 9mm
        • "in principiu pt 8 camere" (R Andrei)
        • 10 buc
      • Flat cables (Vali)
      • pad-plane
        • modificare gauri tehnologice (R Andrei -> Laura -> Bugi -> Costovici 12.08)
        • minim 4buc
      • ecran
        • proiect neschimbat -> pad-plane [ Costovici 12.08
      • baghete
        • modificari desene [Laura -> ProPlastics 19.08]
        • numar 9(8) + 1
      • kapton (Laura, Alex - Philipp)
    • 4
      In-kind contract [costs]
      • Chamber
      • FEE
      • Infrastructure
      Speaker: Alexandru Bercuci (IFIN-HH)

      De discutat cu Claudiu in saptamana 19-23 .08 costuri pentru FEE.

       

      FEB [Jochen] :

      lpGBT: 37 CHF per part
      VTRX+: 210 CHF per part
      picoTDC: 315 CHF per part
      GaN controller: 23 CHF per part
      
    • 5
      FASP bonding [on hold]
      • final conclusions
      • strategy
        TBD* after mCBM24 data taking campaign
      Speaker: Claudiu Schiaua (IFIN-HH/DFH)

      de discutat dupa campania de la mCBM