RPC weekly meeting
Thursday 3 October 2024 -
13:00
Monday 30 September 2024
Tuesday 1 October 2024
Wednesday 2 October 2024
Thursday 3 October 2024
13:10
Status of the twisted pair signal cable for implementation in M0
-
Florin Gila
George Stoian
Gheorghe Caragheorgheopol
Valerica Aprodu
Status of the twisted pair signal cable for implementation in M0
Florin Gila
George Stoian
Gheorghe Caragheorgheopol
Valerica Aprodu
13:10 - 13:20
- Manual of cable manufacturing, labeling and their mapping - Status of the manufacturing of the signal cables
13:20
M0 backplane equipment
-
Gheorghe Caragheorgheopol
Valerica Aprodu
Andrei Radu
George Stoian
Viorel Duta
M0 backplane equipment
Gheorghe Caragheorgheopol
Valerica Aprodu
Andrei Radu
George Stoian
Viorel Duta
13:20 - 13:40
- gas pipe connection - HV polarity labeling
13:40
discussion about the components for the assembling of M0's chambers
-
Florin Gila
Valerica Aprodu
George Stoian
Andrei Radu
discussion about the components for the assembling of M0's chambers
Florin Gila
Valerica Aprodu
George Stoian
Andrei Radu
13:40 - 14:10
- on-going - resistors soldering on HV boards - honeycomb plates preparations - subcomponents assembling - backplane with a connector plate for counter testing - HV connection of MSMGRPC - needed: - Gas distributors for 60 – 56 pieces - Gas distributors for 100 – 24 pieces - Gas distributors for 200 – 48 pieces - Mini-rod for 60 – 136 pieces - Mini-rod for 100 – 48 pieces - Mini-rod for 200 – 96 pieces - Tightening ledges - 72 pieces
14:10
Design of the CBM-TOF inner zone based on the direct flow MSMGRPCs
-
Gheorghe Caragheorgheopol
Laura Radulescu
(
IFIN-HH
)
Viorel Duta
Andrei Radu
Design of the CBM-TOF inner zone based on the direct flow MSMGRPCs
Gheorghe Caragheorgheopol
Laura Radulescu
(
IFIN-HH
)
Viorel Duta
Andrei Radu
14:10 - 14:30
- priority -> design of the second M0 module. -> done! - back panel - mechanical supports - drawings for the housing box for a new order - done - status of the component procurement - Number of detectors by type in the CBM-TOF inner zone: - MRPC1a ( 60 mm) - 40 - MRPC1b (100 mm) - 108 - MRPC1c (200 mm) - 168 -status of the design of the modules of the inner zone - Viorel
14:30
INVENTOR compatibility check and procurement
-
Laura Radulescu
(
IFIN-HH
)
Andrei Naziru
Viorel Duta
INVENTOR compatibility check and procurement
Laura Radulescu
(
IFIN-HH
)
Andrei Naziru
Viorel Duta
14:30 - 14:50
- transfer of knowledge status - status of the procurement - Andrei Naziru
14:50
backup of all files belonging to the design of the CBM-TOF inner zone
-
Mariana Petris
(
National Institute for R&D in Physics and Nuclear Engineering (IFIN-HH), Bucharest
)
backup of all files belonging to the design of the CBM-TOF inner zone
Mariana Petris
(
National Institute for R&D in Physics and Nuclear Engineering (IFIN-HH), Bucharest
)
14:50 - 15:10
- design of the spacers' position - Laura - any update made from last backup - Laura
15:10
Assembling manual
-
Valerica Aprodu
Mariana Petris
(
National Institute for R&D in Physics and Nuclear Engineering (IFIN-HH), Bucharest
)
Assembling manual
Valerica Aprodu
Mariana Petris
(
National Institute for R&D in Physics and Nuclear Engineering (IFIN-HH), Bucharest
)
15:10 - 15:30
- chamber assembling -> in progress - what about module assembling manual? Viorel, Cara, Laura, George, Vali
15:30
Status of the in-kind contract draft
-
Mihai Petrovici
(
National Institute for Physics and Nuclear Engineering (IFIN-HH)
)
Mariana Petris
(
National Institute for R&D in Physics and Nuclear Engineering (IFIN-HH), Bucharest
)
Status of the in-kind contract draft
Mihai Petrovici
(
National Institute for Physics and Nuclear Engineering (IFIN-HH)
)
Mariana Petris
(
National Institute for R&D in Physics and Nuclear Engineering (IFIN-HH), Bucharest
)
15:30 - 15:40
15:40
aob
aob
15:40 - 16:00