RPC weekly meeting
Conference Room
-
-
13:10
→
13:20
Status of the twisted pair signal cable for implementation in M0 10m
- Manual of cable manufacturing, labeling and their mapping
- Status of the manufacturing of the signal cables
Speakers: Florin Gila, George Stoian, Gheorghe Caragheorgheopol, Valerica Aprodu -
13:20
→
13:40
M0 backplane equipment 20m
- gas pipe connection
- HV polarity labeling
Speakers: Andrei Radu, George Stoian, Gheorghe Caragheorgheopol, Valerica Aprodu, Viorel Duta -
13:40
→
14:10
discussion about the components for the assembling of M0's chambers 30m
-
on-going
- resistors soldering on HV boards
- honeycomb plates preparations
- subcomponents assembling
- HV connection of MSMGRPC -
needed:
- Gas distributors for 60 – 56 pieces
- Gas distributors for 100 – 24 pieces
- Gas distributors for 200 – 48 pieces
- Mini-rod for 60 – 136 pieces
- Mini-rod for 100 – 48 pieces
- Mini-rod for 200 – 96 pieces
- Tightening ledges - 72 pieces
Speakers: Andrei Radu, Florin Gila, George Stoian, Valerica Aprodu -
-
14:10
→
14:20
Design of the CBM-TOF inner zone based on the direct flow MSMGRPCs 10m
-
priority -> second M0 module:
- back panel - arrived
- mechanical supports - arrived
- housing box - ordered
- Connector and electrodes PCBs - arrived
-HV CAEN connectors - arrived
- cornier bars ???
- Al bars for housing box assembling ???
- electronics supports for M0? -
Number of detectors by type in the CBM-TOF inner zone:
- MRPC1a ( 60 mm) - 40
- MRPC1b (100 mm) - 108
- MRPC1c (200 mm) - 168
-status of the design of the modules of the inner zone - Viorel
- 2 M3 design ready
- back panels - offers, orders?
- 4 M1 design ready
- 2 M2 design in progress
- electronics supports?Speakers: Andrei Naziru, Laura Radulescu (IFIN-HH), Viorel Duta -
-
14:20
→
14:30
in-beam and in - house tests 10m
- housing box and backplane for in-house and in-beam tests
- housing box - we have
- back plane manufacturaed -> need equipped
- mechanical supports for in house tests - designed
- mechanical supports for in-beam test ?
- mecanical supports for FEE for in-beam tests.
nu exista material pt suporti electronica- dl. Duta se ocupa sa aduca oferta
Speakers: Andrei Radu, Florin Gila, George Stoian, Valerica Aprodu - housing box and backplane for in-house and in-beam tests
-
14:30
→
14:50
INVENTOR compatibility check and procurement 20m
- transfer of knowledge status
- status of the procurement - Andrei Naziru
Speakers: Andrei Naziru, Laura Radulescu (IFIN-HH), Viorel Duta -
14:50
→
15:10
backup of all files belonging to the design of the CBM-TOF inner zone 20m
- design of the spacers' position - Laura
- any update made from last backup - Laura
Speaker: Mariana Petris (National Institute for R&D in Physics and Nuclear Engineering (IFIN-HH), Bucharest) -
15:10
→
15:30
Assembling manual 20m
- chamber assembling -> in progress
- what about module assembling manual? Viorel, Cara, Laura, George, Vali
Speakers: Mariana Petris (National Institute for R&D in Physics and Nuclear Engineering (IFIN-HH), Bucharest), Valerica Aprodu -
15:30
→
15:40
Status of the in-kind contract draft 10mSpeakers: Mariana Petris (National Institute for R&D in Physics and Nuclear Engineering (IFIN-HH), Bucharest), Prof. Mihai Petrovici (National Institute for Physics and Nuclear Engineering (IFIN-HH))
-
15:40
→
16:00
aob 20m
-
13:10
→
13:20