TRD-2D weekly
→
Europe/Bucharest
Conference room Building A (DFH)
Conference room Building A
DFH
Description
Weekly reports on local activities done for the TRD-2D project of the CBM collaboration.
Meeting Access Information
-
Meeting ID: 826 8725 7222
-
Passcode: 723781
-
Direct Link : https://us02web.zoom.us/j/82687257222
Contact
Addendum - end Jan
In-kind contract
- first structure : end Feb
- first draft : end Aug
FEB/FEE development
- FEB test - end Mar design done.
- FASP prod - end Mar
- FASP bonding/test - CERN. end Apr (FASP-PCB check Claudiu)
- FASP packing - end May
- FEB test - end May done and usable
- ADC 8ch 14$/pc. end Apr ordered
- FEB (FASP-FEB, CLK-FEB, OPTIC -FEB) : design end Aug
- FEB (FASP-FEB, CLK-FEB, OPTIC -FEB) : ready end Oct.
- TRY to equip 2 TRD2D (2012 + 2022) to be installed at mCBM
TRD2D prototype testing
- Assembly and Testing manual end Feb
- X rays + Fe end Mar/Apr
- uniformity scan (current measurement - see OROC)
- long term stability and check dark current
- high counting rate ?! to be decided HOW
mCBM data analysis
- TRD2D in Lambda reconstruction end May
TRD proposal for CBM
- Discuss next week a realistic proposal for the list of items and schedule of the TRD2D
FASP-ADC single channel
- submission end Oct
There are minutes attached to this event.